The timing was the same for the Malelane hotel, and actually contravenes recommendations/regulations regarding the implementation of PP processes. Maybe it's different for BARs?

From the document: The table below illustrates medium-to-long term capital investment plan SANParks will be implementing during the course the strategic period.Toko wrote:That is only "project cost" and not an annual budget. It does not say when the money is spent and where it comes from.Richprins wrote:2013-14 SANParks budget, R200 million for Skukuza Hotel (Conference Lodge)
(Up from R165 mil in 2012-13 budget)
Completion then expected end March 2015...
http://www.sanparks.org/assets/docs/abo ... 3-2014.pdf
Page 30
So not sure how /gov money suddenly comes into the equation?
Now inn all earnest the costs in re-erecting a bungalow, definitelyRichprins wrote:To rebuild them, which probably won't happen, would cost the same amount.